To improve reliability of rotary equipment I hereby ORDER:
1. Engineering Supervision Department (Kazeev P.M.):
1.1. To arrange the acceptance test of all new rolling bearings on the vibration diagnostics stand COMPACS®-RPP making reports by engineers of the equipment diagnostics.
2. Materials Management Department (Tyulkin S.P.):
2.1. Arrange the acceptance test of all new rolling bearings on the vibration analysis stand COMPACS®-RPP in the repair department.
2.2. All rolling bearings, suitable for operation in all parameters, in accordance with the conclusion of engineers of the equipment diagnostics of Engineering Supervision Department, must be entered and given to the workshops in accordance with the applications.
2.3. All rolling bearings, not suitable for operation in one of the parameters, must be issued together with the claim of Department of Mechanical Engineering to the supplier.
3. Department of Mechanical Engineering (Karavayev O.I.) must prepare claims to the suppliers after detection of the defects of rolling bearings.
4. First Deputy General Director - Operation and Equipment Maintanence Director Struk Yu.V. shall be charged with monitoring the execution of this Order.
Authors: General Director, Rubinstein L.A., Chief Engineer Luriya V.B., First Deputy General Director - Operation and Equipment Maintanence Director Struk Yu.V / 2001 Download the response
|